Caseware UK (AP4) 2024.0.164 2024.0.164 2025-03-312025-03-312025-03-312025-03-31truetruetrue2024-04-01falsefalse22false 05055108 2024-04-01 2025-03-31 05055108 2023-04-01 2024-03-31 05055108 2025-03-31 05055108 2024-03-31 05055108 2023-04-01 05055108 1 2024-04-01 2025-03-31 05055108 1 2023-04-01 2024-03-31 05055108 2 2024-04-01 2025-03-31 05055108 2 2023-04-01 2024-03-31 05055108 5 2024-04-01 2025-03-31 05055108 5 2023-04-01 2024-03-31 05055108 6 2024-04-01 2025-03-31 05055108 6 2023-04-01 2024-03-31 05055108 d:CompanySecretary1 2024-04-01 2025-03-31 05055108 d:Director1 2024-04-01 2025-03-31 05055108 d:Director2 2024-04-01 2025-03-31 05055108 d:RegisteredOffice 2024-04-01 2025-03-31 05055108 e:Buildings e:LongLeaseholdAssets 2024-04-01 2025-03-31 05055108 e:Buildings e:LongLeaseholdAssets 2025-03-31 05055108 e:Buildings e:LongLeaseholdAssets 2024-03-31 05055108 e:Buildings e:ShortLeaseholdAssets 2024-04-01 2025-03-31 05055108 e:PlantMachinery 2024-04-01 2025-03-31 05055108 e:PlantMachinery 2025-03-31 05055108 e:PlantMachinery 2024-03-31 05055108 e:PlantMachinery e:OwnedOrFreeholdAssets 2024-04-01 2025-03-31 05055108 e:OwnedOrFreeholdAssets 2024-04-01 2025-03-31 05055108 e:CurrentFinancialInstruments 2025-03-31 05055108 e:CurrentFinancialInstruments 2024-03-31 05055108 e:Non-currentFinancialInstruments 2025-03-31 05055108 e:Non-currentFinancialInstruments 2024-03-31 05055108 e:Non-currentFinancialInstruments 6 2025-03-31 05055108 e:Non-currentFinancialInstruments 6 2024-03-31 05055108 e:CurrentFinancialInstruments e:WithinOneYear 2025-03-31 05055108 e:CurrentFinancialInstruments e:WithinOneYear 2024-03-31 05055108 e:Non-currentFinancialInstruments e:AfterOneYear 2025-03-31 05055108 e:Non-currentFinancialInstruments e:AfterOneYear 2024-03-31 05055108 e:Non-currentFinancialInstruments e:BetweenTwoFiveYears 2025-03-31 05055108 e:Non-currentFinancialInstruments e:BetweenTwoFiveYears 2024-03-31 05055108 e:Non-currentFinancialInstruments e:MoreThanFiveYears 2025-03-31 05055108 e:Non-currentFinancialInstruments e:MoreThanFiveYears 2024-03-31 05055108 e:ReportableOperatingSegment1 2024-04-01 2025-03-31 05055108 e:ReportableOperatingSegment1 2023-04-01 2024-03-31 05055108 e:UKTax 2024-04-01 2025-03-31 05055108 e:UKTax 2023-04-01 2024-03-31 05055108 e:ShareCapital 2024-04-01 2025-03-31 05055108 e:ShareCapital 2025-03-31 05055108 e:ShareCapital 2023-04-01 2024-03-31 05055108 e:ShareCapital 2024-03-31 05055108 e:ShareCapital 2023-04-01 05055108 e:OtherMiscellaneousReserve 2024-04-01 2025-03-31 05055108 e:OtherMiscellaneousReserve 2025-03-31 05055108 e:OtherMiscellaneousReserve 1 2024-04-01 2025-03-31 05055108 e:OtherMiscellaneousReserve 2 2024-04-01 2025-03-31 05055108 e:OtherMiscellaneousReserve 2023-04-01 2024-03-31 05055108 e:OtherMiscellaneousReserve 2024-03-31 05055108 e:OtherMiscellaneousReserve 2023-04-01 05055108 e:OtherMiscellaneousReserve 1 2023-04-01 2024-03-31 05055108 e:OtherMiscellaneousReserve 2 2023-04-01 2024-03-31 05055108 e:RetainedEarningsAccumulatedLosses 2024-04-01 2025-03-31 05055108 e:RetainedEarningsAccumulatedLosses 2025-03-31 05055108 e:RetainedEarningsAccumulatedLosses 1 2024-04-01 2025-03-31 05055108 e:RetainedEarningsAccumulatedLosses 2 2024-04-01 2025-03-31 05055108 e:RetainedEarningsAccumulatedLosses 2023-04-01 2024-03-31 05055108 e:RetainedEarningsAccumulatedLosses 2024-03-31 05055108 e:RetainedEarningsAccumulatedLosses 2023-04-01 05055108 e:RetainedEarningsAccumulatedLosses 1 2023-04-01 2024-03-31 05055108 e:RetainedEarningsAccumulatedLosses 2 2023-04-01 2024-03-31 05055108 e:AcceleratedTaxDepreciationDeferredTax 2025-03-31 05055108 e:AcceleratedTaxDepreciationDeferredTax 2024-03-31 05055108 e:OtherDeferredTax 2025-03-31 05055108 e:OtherDeferredTax 2024-03-31 05055108 e:FurtherSpecificTypeProvisionContingentLiability1ComponentTotalProvisionsContingentLiabilities 2024-04-01 2025-03-31 05055108 e:FurtherSpecificTypeProvisionContingentLiability1ComponentTotalProvisionsContingentLiabilities 2025-03-31 05055108 e:FurtherSpecificTypeProvisionContingentLiability1ComponentTotalProvisionsContingentLiabilities 2024-03-31 05055108 d:OrdinaryShareClass1 2024-04-01 2025-03-31 05055108 d:OrdinaryShareClass1 2025-03-31 05055108 d:OrdinaryShareClass1 2024-03-31 05055108 d:FRS102 2024-04-01 2025-03-31 05055108 d:Audited 2024-04-01 2025-03-31 05055108 d:FullAccounts 2024-04-01 2025-03-31 05055108 d:PrivateLimitedCompanyLtd 2024-04-01 2025-03-31 05055108 1 2024-04-01 2025-03-31 05055108 2 2024-04-01 2025-03-31 05055108 9 2024-04-01 2025-03-31 05055108 f:PoundSterling 2024-04-01 2025-03-31 iso4217:GBP xbrli:shares xbrli:pure
Registered number: 05055108










DC PROJECTS (WOLVERHAMPTON) LIMITED

AUDITED
DIRECTORS' REPORT
AND FINANCIAL STATEMENTS

FOR THE YEAR ENDED
31 MARCH 2025
 






 



 






 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

COMPANY INFORMATION


Directors
Mr A. T. S. Parry 
Mr A. W. Hopps 




Company secretary
Mr A. T. S. Parry



Registered number
05055108



Registered office
4 Greengate
Cardale Park

Harrogate

North Yorkshire

HG3 1GY




Independent auditors
Wellden Turnbull Limited
Chartered Accountants & Statutory Auditors

Albany House

Claremont Lane

Esher

Surrey

KT10 9FQ





 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

CONTENTS



Page
Directors' Report
 
 
1 - 2
Independent Auditors' Report
 
 
3 - 6
Profit and Loss Account
 
 
7
Statement of Comprehensive Income
 
 
8
Balance Sheet
 
 
9
Statement of Changes in Equity
 
 
10
Notes to the Financial Statements
 
 
11 - 26


 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
DIRECTORS' REPORT
FOR THE YEAR ENDED 31 MARCH 2025

The Directors present their report and the financial statements for the year ended 31 March 2025.

Directors' responsibilities statement

The Directors are responsible for preparing the Directors' Report and the financial statements in accordance with applicable law and regulations.
 
Company law requires the Directors to prepare financial statements for each financial year. Under that law the Directors have elected to prepare the financial statements in accordance with applicable law and United Kingdom Accounting Standards (United Kingdom Generally Accepted Accounting Practice), including Financial Reporting Standard 102 ‘The Financial Reporting Standard applicable in the UK and Republic of Ireland'. Under company law the Directors must not approve the financial statements unless they are satisfied that they give a true and fair view of the state of affairs of the Company and of the profit or loss of the Company for that period.

 In preparing these financial statements, the Directors are required to:


select suitable accounting policies for the Company's financial statements and then apply them consistently;

make judgements and accounting estimates that are reasonable and prudent;

state whether applicable UK Accounting Standards have been followed, subject to any material departures disclosed and explained in the financial statements;

prepare the financial statements on the going concern basis unless it is inappropriate to presume that the Company will continue in business.

The Directors are responsible for keeping adequate accounting records that are sufficient to show and explain the Company's transactions and disclose with reasonable accuracy at any time the financial position of the Company and to enable them to ensure that the financial statements comply with the Companies Act 2006They are also responsible for safeguarding the assets of the Company and hence for taking reasonable steps for the prevention and detection of fraud and other irregularities.

Principal activity

The Company is engaged in a leisure project under the Private Finance Initiative (PFI), overseeing and funding the construction of one new leisure centre on behalf of Wolverhampton City Council.

Results and dividends

The loss for the year, after taxation, amounted to £18,757 (2024 - profit £326,542).

Dividends paid in the year amounted to £130,000 (2024 - £Nil). The directors have not recommended a final dividend to be paid (2024 - £Nil).

Directors

The Directors who served during the year were:

Mr A. T. S. Parry 
Mr A. W. Hopps 

Page 1

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
DIRECTORS' REPORT (CONTINUED)
FOR THE YEAR ENDED 31 MARCH 2025

Disclosure of information to auditors

Each of the persons who are Directors at the time when this Directors' Report is approved has confirmed that:
 
so far as the Director is aware, there is no relevant audit information of which the Company's auditors are unaware; and

the Director has taken all the steps that ought to have been taken as a Director in order to be aware of any relevant audit information and to establish that the Company's auditors are aware of that information.

Small companies note

In preparing this report, the Directors have taken advantage of the small companies exemptions provided by section 415A of the Companies Act 2006.

This report was approved by the board and signed on its behalf.
 





Mr A. T. S. Parry
Director

Date: 22 December 2025

Page 2

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
INDEPENDENT AUDITORS' REPORT TO THE MEMBERS OF DC PROJECTS (WOLVERHAMPTON) LIMITED
 

Opinion


We have audited the financial statements of DC Projects (Wolverhampton) Limited (the 'Company') for the year ended 31 March 2025, which comprise the Profit and Loss Account, the Statement of Comprehensive Income, the Balance Sheet, the Statement of Changes in Equity and the related notes, including a summary of significant accounting policiesThe financial reporting framework that has been applied in their preparation is applicable law and United Kingdom Accounting Standards, including Financial Reporting Standard 102 ‘The Financial Reporting Standard applicable in the UK and Republic of Ireland' (United Kingdom Generally Accepted Accounting Practice).


In our opinion the financial statements:


give a true and fair view of the state of the Company's affairs as at 31 March 2025 and of its profit for the year then ended;
have been properly prepared in accordance with United Kingdom Generally Accepted Accounting Practice; and
have been prepared in accordance with the requirements of the Companies Act 2006.


Basis for opinion


We conducted our audit in accordance with International Standards on Auditing (UK) (ISAs (UK)) and applicable law. Our responsibilities under those standards are further described in the Auditors' responsibilities for the audit of the financial statements section of our report. We are independent of the Company in accordance with the ethical requirements that are relevant to our audit of the financial statements in the United Kingdom, including the Financial Reporting Council's Ethical Standard and we have fulfilled our other ethical responsibilities in accordance with these requirements. We believe that the audit evidence we have obtained is sufficient and appropriate to provide a basis for our opinion.


Emphasis of matter


We draw attention to note 2.17 of the financial statements, which describes the accounting treatment for fair value gains and losses on financial instrument swaps held by the Company. Our opinion is not modified in this respect.


Conclusions relating to going concern


In auditing the financial statements, we have concluded that the Directors' use of the going concern basis of accounting in the preparation of the financial statements is appropriate.


Based on the work we have performed, we have not identified any material uncertainties relating to events or conditions that, individually or collectively, may cast significant doubt on the Company's ability to continue as a going concern for a period of at least twelve months from when the financial statements are authorised for issue.


Our responsibilities and the responsibilities of the Directors with respect to going concern are described in the relevant sections of this report.


Page 3

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
INDEPENDENT AUDITORS' REPORT TO THE MEMBERS OF DC PROJECTS (WOLVERHAMPTON) LIMITED (CONTINUED)


Other information


The other information comprises the information included in the Annual Report other than the financial statements and our Auditors' Report thereon. The Directors are responsible for the other information contained within the Annual ReportOur opinion on the financial statements does not cover the other information and, except to the extent otherwise explicitly stated in our report, we do not express any form of assurance conclusion thereon. Our responsibility is to read the other information and, in doing so, consider whether the other information is materially inconsistent with the financial statements or our knowledge obtained in the course of the audit, or otherwise appears to be materially misstated. If we identify such material inconsistencies or apparent material misstatements, we are required to determine whether this gives rise to a material misstatement in the financial statements themselves. If, based on the work we have performed, we conclude that there is a material misstatement of this other information, we are required to report that fact.


We have nothing to report in this regard.


Opinion on other matters prescribed by the Companies Act 2006
 

In our opinion, based on the work undertaken in the course of the audit:


the information given in the Directors' Report for the financial year for which the financial statements are prepared is consistent with the financial statements; and
the Directors' Report has been prepared in accordance with applicable legal requirements.


Matters on which we are required to report by exception
 

In the light of the knowledge and understanding of the Company and its environment obtained in the course of the audit, we have not identified material misstatements in the Directors' Report.


We have nothing to report in respect of the following matters in relation to which the Companies Act 2006 requires us to report to you if, in our opinion:


adequate accounting records have not been kept, or returns adequate for our audit have not been received from branches not visited by us; or
the financial statements are not in agreement with the accounting records and returns; or
certain disclosures of Directors' remuneration specified by law are not made; or
we have not received all the information and explanations we require for our audit; or
the Directors were not entitled to prepare the financial statements in accordance with the small companies regime and take advantage of the small companies' exemptions in preparing the Directors' Report and from the requirement to prepare a Strategic Report.


Responsibilities of directors
 

As explained more fully in the Directors' Responsibilities Statement set out on page 1, the Directors are responsible for the preparation of the financial statements and for being satisfied that they give a true and fair view, and for such internal control as the Directors determine is necessary to enable the preparation of financial statements that are free from material misstatement, whether due to fraud or error.


In preparing the financial statements, the Directors are responsible for assessing the Company's ability to continue as a going concern, disclosing, as applicable, matters related to going concern and using the going concern basis of accounting unless the Directors either intend to liquidate the Company or to cease operations, or have no realistic alternative but to do so.


Page 4

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
INDEPENDENT AUDITORS' REPORT TO THE MEMBERS OF DC PROJECTS (WOLVERHAMPTON) LIMITED (CONTINUED)


Auditors' responsibilities for the audit of the financial statements
 

Our objectives are to obtain reasonable assurance about whether the financial statements as a whole are free from material misstatement, whether due to fraud or error, and to issue an Auditors' Report that includes our opinion. Reasonable assurance is a high level of assurance, but is not a guarantee that an audit conducted in accordance with ISAs (UK) will always detect a material misstatement when it exists. Misstatements can arise from fraud or error and are considered material if, individually or in the aggregate, they could reasonably be expected to influence the economic decisions of users taken on the basis of these financial statements.


Irregularities, including fraud, are instances of non-compliance with laws and regulations. We design procedures in line with our responsibilities, outlined above, to detect material misstatements in respect of irregularities, including fraud. We have identified the greatest risk of a material impact on the financial statements from irregularities, including fraud, to relate to the timing and recognition of revenue, and the override of controls by management. We have obtained an understanding of the legal and regulatory frameworks that the Company operates within including both those that directly have an impact on the financial statements and more widely those for which non-compliance could have a significant impact on the Company’s operations and reputation. The Companies Act 2006, employee legislation, health and safety legislation, data protection legislation and UK tax law are those we have identified in this regard. Auditing standards limit the required procedures as to non-compliance with laws and regulations to enquiries of those charged with governance and review of any applicable correspondence. The extent to which our procedures are capable of detecting irregularities, including fraud is detailed below:

Enquiry of management and those charged with governance as to actual and potential litigation and claims;
 
Enquiry of management and those charged with governance to identify any instances of non-compliance with laws and regulations;
 
Performing audit work over the risk of management override of controls, including testing of journal entries and other adjustments for appropriateness, evaluating the business rationale of significant transactions outside the normal course of business, and reviewing accounting estimates for bias;
 
Assessing the reasonableness of revenue and finance income recognised in the period based on contractual terms and obligations and the requirement of accounting standards;
 
Reviewing and challenging assumptions and judgements in respect of significant accounting estimates, regarding the valuation of fixed assets and related impairment assessment, including valuation methodology and financial models and key inputs such as forward cash flow forecasts and associated growth rates and discount rates;
 
Verifying the Company's fair value swap positions to independent third party commercial valuations;
 
Reviewing and challenging the underlying assumptions and valuation methodology used for the valuation of the Company's group and third party loans including assessing the reasonableness of valuation inputs and assumptions in the context of market available data to assess for indicators of management bias;
 
Reviewing the tax provisions of the Company with the assistance of our independent tax specialists; and
 
Reviewing financial statement disclosures and testing to supporting documentation to assess compliance with applicable laws and regulations.




 


Page 5

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
INDEPENDENT AUDITORS' REPORT TO THE MEMBERS OF DC PROJECTS (WOLVERHAMPTON) LIMITED (CONTINUED)


Because of the inherent limitations of an audit, there is a risk that we will not detect all irregularities, including those leading to a material misstatement in the financial statements or non-compliance with regulation. This risk increases the more that compliance with a law or regulation is removed from the events and transactions reflected in the financial statements, as we will be less likely to become aware of instances of non-compliance. The risk is also greater regarding irregularities occurring due to fraud rather than error, as fraud involves intentional concealment, forgery, collusion, omission or misrepresentation.


A further description of our responsibilities for the audit of the financial statements is located on the Financial Reporting Council's website at: www.frc.org.uk/auditorsresponsibilities. This description forms part of our Auditors' Report.


Use of our report
 

This report is made solely to the Company's members, as a body, in accordance with Chapter 3 of Part 16 of the Companies Act 2006Our audit work has been undertaken so that we might state to the Company's members those matters we are required to state to them in an Auditors' Report and for no other purpose. To the fullest extent permitted by law, we do not accept or assume responsibility to anyone other than the Company and the Company's members, as a body, for our audit work, for this report, or for the opinions we have formed.





Mark Nelligan FCA (Senior Statutory Auditor)
  
for and on behalf of
Wellden Turnbull Limited
 
Chartered Accountants
Statutory Auditors
  
Albany House
Claremont Lane
Esher
Surrey
KT10 9FQ

 
Date: 
22 December 2025
Page 6

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

PROFIT AND LOSS ACCOUNT
FOR THE YEAR ENDED 31 MARCH 2025

2025
2024
                                                                                                                          Note  
£
£

  

Turnover
 4 
2,075,201
2,041,985

Cost of sales
  
(1,533,497)
(1,057,724)

Gross profit
  
541,704
984,261

Administrative expenses
  
(133,221)
(94,226)

Operating profit
  
408,483
890,035

Interest receivable and similar income
 7 
45,241
41,547

Interest payable and similar expenses
 8 
(412,850)
(430,311)

Profit before tax
  
40,874
501,271

Tax on profit
 9 
(59,631)
(174,729)

(Loss)/profit for the financial year
  
(18,757)
326,542

The notes on pages 11 to 26 form part of these financial statements.

Page 7

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

STATEMENT OF COMPREHENSIVE INCOME
FOR THE YEAR ENDED 31 MARCH 2025

2025
2024
           Note  
£
£


Profit for the financial year

  

(18,757)
326,542

Other comprehensive income
  


Fair value gains on swaps
 17 
74,241
60,719

Deferred tax arising on fair value adjustments
 18 
(18,560)
(15,180)

Other comprehensive income for the year
  
55,681
45,539

Total comprehensive income for the year
  
36,924
372,081

The notes on pages 11 to 26 form part of these financial statements.

Page 8

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
REGISTERED NUMBER: 05055108

BALANCE SHEET
AS AT 31 MARCH 2025

2025
2024
Note
£
£

Fixed assets
  

Tangible assets
 10 
5,165,195
5,607,923

Current assets
  

Debtors: amounts falling due after more than one year
 11 
24,702
43,262

Debtors: amounts falling due within one year
 11 
177,073
180,187

Cash at bank and in hand
 12 
3,173,470
3,301,369

  
3,375,245
3,524,818

Creditors: amounts falling due within one year
 13 
(1,125,401)
(1,322,167)

Net current assets
  
 
 
2,249,844
 
 
2,202,651

Total assets less current liabilities
  
7,415,039
7,810,574

Creditors: amounts falling due after more than one year
 14 
(6,063,207)
(6,522,591)

Provisions for liabilities
  

Deferred tax
 18 
(188,607)
(196,062)

Other provisions
 19 
(314,906)
(150,526)

  
 
 
(503,513)
 
 
(346,588)

Net assets
  
848,319
941,395


Capital and reserves
  

Called up share capital 
 20 
100,000
100,000

Other reserves
 21 
(74,106)
(129,787)

Profit and loss account
 21 
822,425
971,182

Shareholders' funds
  
848,319
941,395


The Company's financial statements have been prepared in accordance with the provisions applicable to companies subject to the small companies regime.

The financial statements were approved and authorised for issue by the board and were signed on its behalf by: 




Mr A. T. S. Parry
Director

Date: 22 December 2025

The notes on pages 11 to 26 form part of these financial statements.

Page 9

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

STATEMENT OF CHANGES IN EQUITY
FOR THE YEAR ENDED 31 MARCH 2025


Called up share capital
Other reserves - Hedging reserve
Profit and loss account
Total equity

£
£
£
£


At 1 April 2023
100,000
(175,326)
644,640
569,314


Comprehensive income for the year

Profit for the year

-
-
326,542
326,542

Fair value gains on swaps
-
60,719
-
60,719

Deferred tax arising on fair value adjustments
-
(15,180)
-
(15,180)


Other comprehensive income for the year
-
45,539
-
45,539


Total comprehensive income for the year
-
45,539
326,542
372,081



At 1 April 2024
100,000
(129,787)
971,182
941,395


Comprehensive income for the year

Loss for the year

-
-
(18,757)
(18,757)

Fair value gains on swaps
-
74,241
-
74,241

Deferred tax arising on fair value adjustments
-
(18,560)
-
(18,560)


Other comprehensive income for the year
-
55,681
-
55,681


Total comprehensive income for the year
-
55,681
(18,757)
36,924


Contributions by and distributions to owners

Dividends: Equity capital
-
-
(130,000)
(130,000)


At 31 March 2025
100,000
(74,106)
822,425
848,319


The notes on pages 11 to 26 form part of these financial statements.

Page 10

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31 MARCH 2025

1.


General information

DC Projects (Wolverhampton) Limited is a private Company, limited by shares, incorporated in England and Wales, registered number 05055108. The registered office is 4 Greengate, Cardale Park, Harrogate, North Yorkshire, HG3 1GY.

2.Accounting policies

 
2.1

Basis of preparation of financial statements

The financial statements have been prepared under the historical cost convention unless otherwise specified within these accounting policies and in accordance with Financial Reporting Standard 102, the Financial Reporting Standard applicable in the UK and the Republic of Ireland and the Companies Act 2006.

The preparation of financial statements in compliance with FRS 102 requires the use of certain critical accounting estimates. It also requires management to exercise judgement in applying the Company's accounting policies (see note 3).

These financial statements are presented in sterling which is the functional currency of the Company and rounded to the nearest £.

The following principal accounting policies have been applied:

  
2.2

Compliance with accounting standards

The accounts have been prepared in accordance with the provisions of FRS 102, with the exception of matters disclosed in note 2.17. Management have concluded that the financial statements present a true and fair view of the Company's affairs as at 31 March 2025 and its loss for the year then ended.

 
2.3

Financial Reporting Standard 102 - reduced disclosure exemptions

The Company has taken advantage of the following disclosure exemptions in preparing these financial statements, as permitted by the FRS 102 "The Financial Reporting Standard applicable in the UK and Republic of Ireland":
the requirements of Section 7 Statement of Cash Flows;
the requirements of Section 3 Financial Statement Presentation paragraph 3.17(d);
the requirements of Section 33 Related Party Disclosures paragraph 33.7.

This information is included in the consolidated financial statements of Cardale PFI Investments Limited as at 31 March 2025 and these financial statements may be obtained from 4 Greengate, Cardale Park, Harrogate, North Yorkshire, HG3 1GY.

Page 11

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31 MARCH 2025

2.Accounting policies (continued)

 
2.4

Going concern

The financial statements have been prepared on a going concern basis. The Company is in a net asset position, and although it has made a loss in the period, it has generated sufficient cash from operations to meet its liabilities as they fall due. In assessing the appropriateness of the going concern basis of preparation, the Directors have taken into account the key risks of the business, including the current economic global uncertainties. In doing so the Directors have considered the Company’s business model and availability of cash resources. The Directors have prepared projected cash flow information for at least twelve months from the date of their approval of these financial statements. On the basis of this cash flow information, the Directors consider that the Company will continue to operate within the long term facility currently agreed. In addition, during the operational phase of the project, sufficient cash flow is projected to be generated to allow the Company to meet continue to meet its liabilities as they fall due for payment.

The Company’s senior loan is repayable by 31 March 2033 and is supported by the future cash flows from a PFI contract with Wolverhampton City Council which matures in 2036. Having undertaken this assessment the Directors consider it is appropriate to prepare the financial statements on a going concern basis. The financial statements do not include any adjustments that would result from the basis of preparation being inappropriate.

 
2.5

Revenue

Revenue is recognised to the extent that it is probable that the economic benefits will flow to the Company and the revenue can be reliably measured. Revenue is measured as the fair value of the consideration received or receivable, excluding discounts, rebates, value added tax and other sales taxes. The following criteria must also be met before revenue is recognised:

Rendering of services

Revenue from a contract to provide services is recognised in the period in which the services are provided in accordance with the stage of completion of the contract when all of the following conditions are satisfied:
the amount of revenue can be measured reliably;
it is probable that the Company will receive the consideration due under the contract;
the stage of completion of the contract at the end of the reporting period can be measured reliably; and
the costs incurred and the costs to complete the contract can be measured reliably.

The Company recognises income when it has fully fulfilled its contractual obligations. In accordance with FRS 102 the Company includes sales and purchase transactions related to variations under the original contract where the benefits and risks are retained by the Company, within the financial statements as turnover and operating costs.

Transactions to which the Company does not have access to all the significant benefits and risks are excluded from the financial statements.

Page 12

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31 MARCH 2025

2.Accounting policies (continued)

  
2.6

Service concession arrangements - Accounting by operators

Under transitional rules, the company has elected not to apply FRS102 to Service concession arrangements that were entered into before the date of transition. These relate to PFI contracts which under FRS 5 Application Note F "Private Finance Initiative and Similar Contracts" the Directors are of the opinion that the Company bears the majority of the risks and benefits of the leasehold property and as a result this asset has been disclosed as a tangible fixed asset. Revenues received from Wolverhampton City Council for its leisure centre are credited to the profit and loss account as received.

 
2.7

Interest income

Interest income is recognised in profit or loss using the effective interest method.

 
2.8

Finance costs

Finance costs are charged to profit or loss over the term of the debt using the effective interest method so that the amount charged is at a constant rate on the carrying amount. Issue costs are initially recognised as a reduction in the proceeds of the associated capital instrument.

 
2.9

Current and deferred taxation

The tax expense for the year comprises current and deferred tax. Tax is recognised in profit or loss except that a charge attributable to an item of income and expense recognised as other comprehensive income or to an item recognised directly in equity is also recognised in other comprehensive income or directly in equity respectively.

The current income tax charge is calculated on the basis of tax rates and laws that have been enacted or substantively enacted by the balance sheet date in the countries where the Company operates and generates income.

Deferred tax balances are recognised in respect of all timing differences that have originated but not reversed by the balance sheet date, except that:
The recognition of deferred tax assets is limited to the extent that it is probable that they will be recovered against the reversal of deferred tax liabilities or other future taxable profits; and
Any deferred tax balances are reversed if and when all conditions for retaining associated tax allowances have been met.

Deferred tax balances are not recognised in respect of permanent differences except in respect of business combinations, when deferred tax is recognised on the differences between the fair values of assets acquired and the future tax deductions available for them and the differences between the fair values of liabilities acquired and the amount that will be assessed for tax. Deferred tax is determined using tax rates and laws that have been enacted or substantively enacted by the balance sheet date.


Page 13

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31 MARCH 2025

2.Accounting policies (continued)

 
2.10

Tangible fixed assets

Tangible fixed assets under the cost model are stated at historical cost less accumulated depreciation and any accumulated impairment losses. Historical cost includes expenditure that is directly attributable to bringing the asset to the location and condition necessary for it to be capable of operating in the manner intended by management.

Depreciation is charged so as to allocate the cost of assets less their residual value over their estimated useful lives, using the straight-line method.

Depreciation is provided on the following basis:

Building
-
the remainder of the PFI contract
Plant and machinery
-
2-10 years or the remainder of the PFI contract

The assets' residual values, useful lives and depreciation methods are reviewed, and adjusted prospectively if appropriate, or if there is an indication of a significant change since the last reporting date.

Gains and losses on disposals are determined by comparing the proceeds with the carrying amount and are recognised in profit or loss.

 
2.11

Debtors

Short-term debtors are measured at transaction price, less any impairment. Loans receivable are measured initially at fair value, net of transaction costs, and are measured subsequently at amortised cost using the effective interest method, less any impairment.

 
2.12

Cash and cash equivalents

Cash is represented by cash in hand and deposits with financial institutions repayable without penalty on notice of not more than 24 hours. Cash equivalents are highly liquid investments that mature in no more than three months from the date of acquisition and that are readily convertible to known amounts of cash with insignificant risk of change in value.

 
2.13

Creditors

Short-term creditors are measured at the transaction price. Other financial liabilities, including bank loans, are measured initially at fair value, net of transaction costs, and are measured subsequently at amortised cost using the effective interest method.

  
2.14

Provisions for liabilities

Provisions are made where an event has taken place that gives the Company a legal or constructive obligation that probably requires settlement by a transfer of economic benefit, and a reliable estimate can be made of the amount of the obligation.

Provisions are charged as an expense to profit or loss in the year that the Company becomes aware of the obligation, and are measured at the best estimate at the balance sheet date of the expenditure required to settle the obligation, taking into account relevant risks and uncertainties. 

When payments are eventually made, they are charged to the provision carried in the Balance Sheet.

Page 14

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31 MARCH 2025

2.Accounting policies (continued)

 
2.15

Financial instruments

The Company has elected to apply the provisions of Section 11 “Basic Financial Instruments” of FRS 102 to all of its financial instruments.

The Company has elected to apply the recognition and measurement provisions of IFRS 9 Financial Instruments (as adopted by the UK Endorsement Board) with the disclosure requirements of Sections 11 and 12 and the other presentation requirements of FRS 102.

Financial instruments are recognised in the Company's Balance Sheet when the Company becomes party to the contractual provisions of the instrument.

Financial assets and liabilities are offset, with the net amounts presented in the financial statements, when there is a legally enforceable right to set off the recognised amounts and there is an intention to settle on a net basis or to realise the asset and settle the liability simultaneously.

Basic financial assets

Basic financial assets, which include trade and other receivables, cash and bank balances, are initially measured at their transaction price including transaction costs and are subsequently carried at their amortised cost using the effective interest method, less any provision for impairment, unless the arrangement constitutes a financing transaction, where the transaction is measured at the present value of the future receipts discounted at a market rate of interest.

Discounting is omitted where the effect of discounting is immaterial. The Company's cash and cash equivalents, trade and most other receivables due with the operating cycle fall into this category of financial instruments.

Other financial assets

Other financial assets, which includes investments in equity instruments which are not classified as subsidiaries, associates or joint ventures, are initially measured at fair value, which is normally the recognised transaction price. Such assets are subsequently measured at fair value with the changes in fair value being recognised in the profit or loss. Where other financial assets are not publicly traded, hence their fair value cannot be measured reliably, they are measured at cost less impairment.

Impairment of financial assets

Financial assets are assessed for indicators of impairment at each reporting date. 

Financial assets are impaired when events, subsequent to their initial recognition, indicate the estimated future cash flows derived from the financial asset(s) have been adversely impacted. The impairment loss will be the difference between the current carrying amount and the present value of the future cash flows at the asset(s) original effective interest rate.

If there is a favourable change in relation to the events surrounding the impairment loss then the impairment can be reviewed for possible reversal. The reversal will not cause the current carrying amount to exceed the original carrying amount had the impairment not been recognised. The impairment reversal is recognised in the profit or loss.

Financial liabilities

Financial liabilities and equity instruments are classified according to the substance of the contractual arrangements entered into. An equity instrument is any contract that evidences a residual interest in the assets of the Company after the deduction of all its liabilities.

Page 15

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31 MARCH 2025

2.Accounting policies (continued)


2.15
Financial instruments (continued)

Basic financial liabilities, which include trade and other payables, bank loans and other loans are initially measured at their transaction price after transaction costs. When this constitutes a financing transaction, whereby the debt instrument is measured at the present value of the future payments discounted at a market rate of interest. Discounting is omitted where the effect of discounting is immaterial.

Debt instruments are subsequently carried at their amortised cost using the effective interest rate method.

Trade payables are obligations to pay for goods and services that have been acquired in the ordinary course of business from suppliers. Trade payables are classified as current liabilities if the payment is due within one year. If not, they represent non-current liabilities. Trade payables are initially recognised at their transaction price and subsequently are measured at amortised cost using the effective interest method. Discounting is omitted where the effect of discounting is immaterial.

Derecognition of financial instruments

Derecognition of financial assets

Financial assets are derecognised when their contractual right to future cash flow expire, or are settled, or when the Company transfers the asset and substantially all the risks and rewards of ownership to another party. If significant risks and rewards of ownership are retained after the transfer to another party, then the Company will continue to recognise the value of the portion of the risks and rewards retained.

Derecognition of financial liabilities

Financial liabilities are derecognised when the Company's contractual obligations expire or are discharged or cancelled.

Derivatives, including interest rate and inflation swaps, are not basic financial instruments.

Page 16

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31 MARCH 2025

2.Accounting policies (continued)

  
2.16

Derivatives

Derivatives are initially recognised at fair value on the date a derivative contract is entered into and are subsequently re-measured to fair value at each reporting date. Fair value gains and losses are recognised in the statement of comprehensive income unless hedge accounting is applied and the hedge is a cash flow hedge.

To qualify for hedge accounting, the Company documents the hedged item, the hedging instrument and the hedging relationship between them and the causes of hedge ineffectiveness.

The Company elects to adopt hedge accounting for interest rate swaps (the 'swaps') where:

The swaps are a qualifying hedging instrument with an external party that hedges rate risk on a loan, part of the nominal amount of a loan, or a group of loans managed together that share the same risk and that qualify as a hedged item;

The hedging relationship between the swaps and the interest rate risk on the loan is consistent with the risk management objectives for undertaking hedges (i.e. to manage the risk that fixed interest rates become unfavourable in comparison to current market rates or the variability in cash flows arising from variable interest rates); and

The change in the fair value of the swaps is expected to move inversely to the change in the fair value of the interest rate risk on the loan.

 
2.17

Hedge accounting

The Company uses variable to fixed interest rate swaps to manage its exposure to interest rate cash flow on its variable debt. These derivatives are measured at fair value at each balance sheet date.

To better reflect the nature of the long term financing structure in operation and in a modification to accounting standards, all cumulative hedging gains or losses on the hedged item are recognised as an asset or liability with a corresponding gain or loss recognised in the statement of comprehensive income. This treatment better reflects the financing profile in operation across the life of the structure.

 
2.18

Dividends

Equity dividends are recognised when they become legally payable. Interim equity dividends are recognised when paid. Final equity dividends are recognised when approved by the shareholders at an annual general meeting.

Page 17

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31 MARCH 2025

3.


Judgements in applying accounting policies and key sources of estimation uncertainty

The preparation of financial statements in conformity with FRS102 requires management to make judgements, estimates and assumptions that affect the application of policies and reported amounts of assets, liabilities, income and expenses. The estimates and associated assumptions are based upon historical experience and various other factors that are believed to be reasonable under the circumstances, the results of which form the basis of making judgements about carrying values of assets and liabilities that are not readily available from other sources.

Critical accounting estimates and assumptions

The Company makes estimates and assumptions concerning the future. The resulting accounting estimates and assumptions will, by definition, seldom equal the actual results.

Critical areas of judgement

The Company makes judgements in applying its accounting policies as described below:
 
The recoverability of the amounts recoverable on long term contracts is based on the receipt of the unitary fee in accordance with the contractual payment mechanisms contained in the project agreement with its client, Wolverhampton City Council.
 
The depreciation charge calculated for the fixed assets requires estimations and judgements on their useful lives. This will affect the values of assets and expenses in the accounts.
 
As set out in note 14, the Group's bank borrowings attract interest at a variable rate based on SONIA, the risk free rate administered by the Bank of England. Bank loans are held at amortised cost which requires the Directors to forecast the expected interest payable over the life of the loan and recognise, in the profit and loss account, interest annually at an effective rate. Each year end the Directors update their forecasts and recognise any difference between actual and forecast interest payable as an adjustment to the effective interest expense. Forecasts require an estimation as to future SONIA rates, based on current market data. Actual rates will vary from forecast over the loan lifetime, rendering the effective interest rate calculated an estimate subject to these variations. If interest payable over the life of the loan were to be considerably different to the Directors forecasts there could be a material impact on the carrying value of the bank loans and associated interest payable expense.
 
An estimation is required on the reasonableness of future costs when accounting for lifecycle maintenance requirements. This is assessed based on historical costs which have been incurred and the future forecast of maintenance work contractually required. Actual costs will vary from forecast over the contract’s life rendering the lifecycle costs as an estimate subject to these variations (see note 19).

The estimates and underlying assumptions are reviewed on an ongoing basis. Revisions to accounting estimates are recognised in the period in which the estimate is revised if the revision affects only that period or in the period of revision and future periods if the revision affects both current and future periods.

Page 18

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31 MARCH 2025

4.


Turnover

An analysis of turnover by class of business is as follows:


2025
2024
£
£

Unitary charge
2,075,201
2,041,985


All turnover arose within the United Kingdom.


5.


Auditors' remuneration

The audit fee for 31 March 2025 and 31 March 2024 has been borne by the parent company Leisure Infrastructure Investors Limited.





6.


Employees

The average monthly number of employees, including the Directors, during the year was as follows:


        2025
        2024
            No.
            No.







Directors
2
2

During the year, no director received any emoluments (2024 - £Nil).


7.


Interest receivable

2025
2024
£
£


Other interest receivable
45,241
41,547


8.


Interest payable and similar expenses

2025
2024
£
£


Bank interest payable
256,666
269,571

Other loan interest payable
156,184
160,740

412,850
430,311

Page 19

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31 MARCH 2025

9.


Taxation


2025
2024
£
£

Corporation tax


Current tax on profits for the year
67,086
178,737


Deferred tax


Origination and reversal of timing differences
(7,455)
(4,008)


Taxation on profit on ordinary activities
59,631
174,729

Factors affecting tax charge for the year

The tax assessed for the year is higher than (2024 - higher than) the standard rate of corporation tax in the UK of25% (2024 - 25%). The differences are explained below:

2025
2024
£
£


Profit on ordinary activities before tax
40,874
501,271


(Loss)/profit on ordinary activities multiplied by standard rate of corporation tax in the UK of 25% (2024 - 25%)
(31,246)
125,318

Effects of:


Other timing differences leading to an increase (decrease) in taxation
90,877
49,411

Total tax charge for the year
59,631
174,729


Factors that may affect future tax charges

There are no factors affecting future tax charges. Deferred taxation has been provided at 25%.

Page 20

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31 MARCH 2025

10.


Tangible fixed assets





Building
Plant and machinery
Total

£
£
£



Cost or valuation


At 1 April 2024
13,286,792
501,251
13,788,043



At 31 March 2025

13,286,792
501,251
13,788,043



Depreciation


At 1 April 2024
7,680,695
499,423
8,180,118


Charge for the year on owned assets
442,586
144
442,730



At 31 March 2025

8,123,281
499,567
8,622,848



Net book value



At 31 March 2025
5,163,511
1,684
5,165,195



At 31 March 2024
5,606,096
1,827
5,607,923

Finance costs of £500,318 (2024 - £500,318) have been capitalised within tangible fixed assets. 

Assets held under PFI contracts have a net book value of £5,165,195 (2024 - £5,607,923)


11.


Debtors

2025
2024
£
£

Due after more than one year

Deferred tax asset
24,702
43,262


2025
2024
£
£

Due within one year

Trade debtors
3,625
10,481

Prepayments and accrued income
173,448
169,706

177,073
180,187


Page 21

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31 MARCH 2025

12.


Cash and cash equivalents

2025
2024
£
£

Cash at bank and in hand
3,173,470
3,301,369



13.


Creditors: Amounts falling due within one year

2025
2024
£
£

Bank loans
239,482
236,429

Trade creditors
271,480
357,378

Amounts owed to group undertakings
178,739
356,430

Group relief payable
67,086
178,738

Taxation and social security
66,432
73,168

Accruals and deferred income
302,182
120,024

1,125,401
1,322,167


Page 22

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31 MARCH 2025

14.


Creditors: Amounts falling due after more than one year

2025
2024
£
£

Bank loans
3,490,617
3,730,097

Amounts owed to group undertakings
1,112,687
1,141,682

Accruals and deferred income
1,361,095
1,477,763

Fair value of derivative contracts
98,808
173,049

6,063,207
6,522,591


Secured loans

The bank loan is secured against all assets of the Company. The interest rate margin over 6 Month GBP SONIA is 0.95%.

On 16 May 2005 the Company entered into a PFI contract with Wolverhampton City Council. Barclays Bank PLC issued a Base Credit Facility loan of £1,384,000 which is repayable semi-annually from September 2007. Further monthly drawdowns were permitted on the Base Credit Facility as per the agreement schedule. During the year loan repayments were made of £254,215 (2024 - £259,862). The Company had an outstanding balance on the loan before unamortised debt issue costs of £3,872,386 (2024 - £4,126,601) at 31 March 2025.

The senior bank loan is matched by an interest rate swap which effectively fixes the interest on the loan at 4.87% over the period of the loan. This excludes the 0.95% margin cost which remains payable by the company on the original loan.

Amounts owed to group undertakings are repayable as shown in note 15. The interest being charged is at a fixed rate of 13.89% p.a on a semi annual basis.

Included within creditors falling due after more than one year is an amount £2,944,864 (2024 - £3,484,532) in respect of liabilities which fall due for payment after more than five years from the balance sheet date.

Page 23

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31 MARCH 2025

15.


Loans


Analysis of the maturity of loans is given below:


2025
2024
£
£

Amounts falling due within one year

Bank loans
239,482
236,429


Amounts falling due 2-5 years

Bank loans
1,658,440
1,387,247

Amounts falling due after more than 5 years

Bank loans
1,832,177
2,342,850

Amounts owed to group undertakings
1,112,687
1,141,682

2,944,864
3,484,532

4,842,786
5,108,208



16.


Basic financial instruments

Financial assets held that are debt instruments measured at amortised cost amounted to £3,625 (2024 - £10,481).

Financial liabilities held that are debt instruments measured at amortised cost amounted to £5,293,005 (2024 - £5,822,016).


17.


Complex financial instruments

The fair value of the Company’s derivatives are as follows:

                                                                                        
 Principal                          Fair value

2025
2024
2025
2024
£
£
£
£
Interest rate swap contracts

(3,872,385)

(4,126,602)

(98,808)
 
(173,049)
 

The Company uses derivatives to manage the exposure to interest rate on its senior debt. The fair values are calculated using valuation techniques, the inputs for which are based on market data at the balance sheet date.
 
The fair value of the interest swap is determined using the forward curve for 6 Month GBP SONIA.

The swap meets the conditions for hedge accounting, as set out in the accounting policies.

Page 24

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31 MARCH 2025

18.


Deferred taxation




2025
2024


£

£






At beginning of year
(152,800)
(141,628)


Credited/(charged) to profit or loss
7,455
4,008


Charged to other comprehensive income
(18,560)
(15,180)



At end of year
(163,905)
(152,800)

The deferred tax balance is made up as follows:

2025
2024
£
£


Accelerated capital allowances
(188,607)
(196,062)

Timing differences arising from fair value adjustments
24,702
43,262

(163,905)
(152,800)

Comprising:

Asset - due after one year (see note 11)
24,702
43,262

Liability
(188,607)
(196,062)

(163,905)
(152,800)



19.


Provisions




Lifecycle provision

£





At 1 April 2024
150,526


Charged to profit or loss
164,380



At 31 March 2025
314,906

The Company has a contractual obligation to provide for renewal of the properties provided under the PFI contract. The provision balance has been reviewed and is deemed reasonable in accordance with expected costs for the repair and/or renewal of the properties.

Page 25

 
DC PROJECTS (WOLVERHAMPTON) LIMITED
 

 
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31 MARCH 2025

20.


Share capital

2025
2024
£
£
Allotted, called up and fully paid



100,000 (2024 - 100,000) Ordinary shares of £1.00 each
100,000
100,000



21.


Reserves

Other reserves

Other reserves relates to the hedging reserve which represents movements in the fair value of the interest rate swap derivatives and associated deferred tax.

Profit and loss account

The profit and loss account represents cumulative profits and losses net of all adjustments.


22.


Related party transactions

Fees of £26,202 (2024 - £27,363) have been charged by an undertaking related by virtue of common directors and shareholders. At the year-end the related undertaking was owed £2,868 (2024 - £2,762) by the Company.

The Company has taken advantage of FRS102 section 33 paragraph 1A not to disclose transactions with wholly owned group members.


23.


Controlling party

The ultimate parent undertaking and controlling party is Cardale PFI Investments Limited.

Consolidated financial statements are available from the registered office at 4 Greengate, Cardale Park, Harrogate, North Yorkshire, HG3 1GY.


Page 26