| During the year, the company paid £239,520 in advance under a contract for the supply and construction of a solar photovoltaic power system in Hong Kong. As at 31 December 2025, construction of the system had not commenced and the project remained in the preparatory stage. Accordingly, the amount has been recognised as a capital advance within debtors. No depreciation has been charged in respect of the project during the year.
Debtors 2025 2024
Capital advance for solar power system £239,520 £ Nil
Other debtors £1,315 £23,562
Total debtors £240,835 £23,562 |